For nearly 50 years, NASA has planned a mission to send an uncrewed spacecraft to Mars to collect rock and soil samples and return them to Earth. Budgetary constraints and technological hurdles delayed the project’s launch.
The mission’s first phase finally launched on February 18, 2021, with the Perseverance rover beginning sample collection. Now, four years later, the entire billion-dollar mission faces potential cancellation.
NASA Administrator Bill Nelson acknowledged escalating costs and missed deadlines, stating that without significant changes, the sample retrieval mission might not proceed.
Nelson explained that projected costs reached $11 billion, with sample return not expected until 2040, prompting him to halt the mission in its current form.
While Nelson stopped the original plan, NASA is exploring partnerships with private companies like SpaceX and Blue Origin to reduce costs. The mission’s challenges highlight the risks of overly complex and expensive projects with insufficient initial planning.
Perseverance has been successful in studying Martian soil, atmosphere, and terrain, but sample return remains a primary objective. The initial plan involved a single spacecraft to collect and return samples, but this “grab-and-go” approach limited scientific scope.
Instead, Perseverance collected samples from various locations within the Jezero Crater, a former lakebed. These diverse samples will provide insights into Mars’ history.
Returning these scattered samples requires multiple spacecraft, escalating costs to $11 billion and delaying the return until the mid-to-late 2030s. A $5 billion budget cut further hampered progress.
Nelson emphasized the mission’s uncontrolled growth and the impossibility of accomplishing everything with reduced funding.
While the original plan is shelved, NASA is soliciting bids from private companies to provide the Mars lander and ascent vehicle, possibly utilizing SpaceX’s or Blue Origin’s launch capabilities.
Alternatively, NASA might handle more work internally, using a sky crane system for landing, leading to smaller, less expensive vehicles. Under either scenario, the European Space Agency (ESA) would still provide the Earth-return spacecraft.
These revised plans would cost between $5.8 billion and $7.7 billion.
Cost reductions could accelerate the timeline, with potential launch dates as early as 2030 for the ESA return vehicle, and 2035 for the fetch and ascent vehicles.
The future of the mission will also depend on political factors and discussions with the incoming NASA administration. Nelson expressed hope that the new administration will prioritize Mars Sample Return.